A Sofar showing an ID code has stopped doing its job, at least for now. Each hour it sits there is solar you are not using and power you buy back at full price. Some ID codes are about safety rather than savings: ID56, and ID12 on a string inverter, mean the inverter has found current leaking from the solar wiring to earth, or the insulation that stops it failing.
Sofar has made inverters since 2015 and is supported through Australian distributors. Some faults inside the unit are repairable and some are not. With Sofar the model matters too, because the same ID number can mean one thing on a string inverter and another on a HYD hybrid. Plenty of codes turn out to be simple once that is known: the grid, a setting, or how the strings are wired.
Dealt with early, a setting or a connector is a short job. Left alone, a protection fault that keeps repeating can lock the inverter out until the cause is fixed, and Sofar's ID65 to ID77 are exactly that kind of lockout.
Find your code in the table below to see what it means and how urgent it is. If your home is in Adelaide, the Adelaide Hills, Gawler, the Barossa, the Fleurieu, Murray Bridge and Yorke Peninsula in South Australia, or North Brisbane, Caboolture, Bribie Island, the Sunshine Coast, Noosa and Gympie in Queensland, our own licensed electricians will go through it with you over the phone for free before anyone drives out. Check your postcode to see if we cover you.
The model is printed on the label on the side of the unit. Knowing which family you have matters with Sofar, because a few ID numbers mean different things on each.
Sofar shows a fault as ID followed by a number, so ID01 is grid voltage too high and ID56 is an insulation fault. Every code is below, grouped by what it relates to: the grid and mains supply, the panel input and power output, insulation and earth faults, the unit's internal hardware, the battery, and monitoring. The number in brackets after each code's name is its source in the reference list.
We always err on the cautious side: when a code sits between two ratings, it gets the higher one.
The mains grid coming into the unit: voltage, frequency and outages. Many of these are the grid, not the inverter, and clear on their own. 5 wait and watch.
| Error code | What it means | What to do |
|---|---|---|
| ID01Sofar ID01 | Grid voltage too high[1] The mains voltage at the inverter went above the limit it is allowed to export at, so it disconnected. It reconnects by itself when the grid settles; if it happens most sunny afternoons the cable run or the street voltage needs checking. Safe steps in the lookup |
Wait and watch |
| ID02Sofar ID02 | Grid voltage too low[1] The mains voltage dropped below the inverter's lower limit, so it stopped exporting. This is almost always the grid, a brownout or a switched-off solar breaker, and clears by itself. Safe steps in the lookup |
Wait and watch |
| ID03Sofar ID03 | Grid frequency too high[1] The grid frequency went above the inverter's limit for a moment and it disconnected. It reconnects by itself once the grid is steady again. Safe steps in the lookup |
Wait and watch |
| ID04Sofar ID04 | Grid frequency too low[1] The grid frequency dipped below the inverter's limit and it disconnected. It reconnects by itself once the grid is steady again. Safe steps in the lookup |
Wait and watch |
| ID82Sofar ID82 | Cutting back for grid frequency[1] The inverter is reducing its output because the grid frequency is high, which the grid rules require. It is not a fault and returns to normal on its own. Safe steps in the lookup |
Wait and watch |
The DC input from the panels and the power the unit puts out: string voltage, low light, overloads and output limits. 2 stop and call, 2 worth a look, 1 wait and watch.
| Error code | What it means | What to do |
|---|---|---|
| ID05Sofar ID05 | Panel voltage too low[1][2] On a Sofar string inverter, the voltage from the panels is below the minimum it needs to start, which is normal at dawn and dusk but a string design problem if it stays all day. On a HYD hybrid the same number means the battery voltage is too high. Safe steps in the lookup |
Wait and watch |
| ID09Sofar ID09 | Panel voltage too high[1][2] On a Sofar string inverter, the voltage from the panels is above what the inverter can accept, usually too many panels in one string, which shows up most on cold clear mornings. On a HYD hybrid the same number is an internal bus overvoltage trip; either way it needs an electrician if it comes back. Bus faults are internal, so we treat them as a call. Safe steps in the lookup |
Stop and call |
| ID10Sofar ID10 | Panel input imbalance[1][2] On a Sofar string inverter, the current from the two panel inputs is uneven, usually because the input mode is set to parallel when the strings are different. On a HYD hybrid the same number is an internal boost-stage overvoltage trip. A restart may clear it; if it comes back the settings or the inverter need an electrician. Over-voltage, over-current and short-circuit faults can damage hardware, so we treat them as a call. Safe steps in the lookup |
Stop and call |
| ID81Sofar ID81 | Cutting back for heat[1] The inverter is reducing its output because it is running hot. This is normal on very hot days; if it happens often or in mild weather the mounting spot or cooling needs a look. Safe steps in the lookup |
Worth a look |
| ID83Sofar ID83 | Remote limit or shutdown[1] The inverter has cut back (ID83) or switched off (ID84) because it received a remote command, for example from an export-limit device or the network. If nothing should be sending that, the control signal wiring needs checking. Safe steps in the lookup |
Worth a look |
Insulation, earth and leakage faults on the solar panel side. These are safety faults: live DC wiring may be leaking to earth somewhere on the roof. 4 stop and call.
| Error code | What it means | What to do |
|---|---|---|
| ID12Sofar ID12 | Earth leakage fault[1][2] On a Sofar string inverter, the inverter measured current leaking to earth from the solar wiring, usually damaged cable insulation or water in a connector. On a HYD hybrid the same number is a battery overcurrent trip. A one-off in wet weather can clear itself, but a repeat is a safety issue and needs an electrician. Safe steps in the lookup |
Stop and call |
| ID20Sofar ID20 | Leakage sensor fault[1] The inverter's own earth-leakage sensor has failed its check, as opposed to finding a real leak. If a restart does not clear it the sensor or board inside has failed. Safe steps in the lookup |
Stop and call |
| ID56Sofar ID56 | Panel insulation fault[1] The inverter found too little insulation between the panel wiring and earth, usually water in a connector or isolator, a chafed cable or a damaged panel. It is a safety trip and needs an electrician to find the fault. Safe steps in the lookup |
Stop and call |
| ID60Sofar ID60 | Earth connection fault[3] On a Sofar hybrid, the earth wire on the AC output is missing or has a poor connection, so the inverter will not export until it is fixed. It needs an electrician. Safe steps in the lookup |
Stop and call |
The unit's own electronics: relays, sensors, the DC bus, memory and its self-checks. Nearly all of these need an electrician. 18 stop and call, 2 worth a look.
| Error code | What it means | What to do |
|---|---|---|
| ID14Sofar ID14 | Panel input overcurrent[1][2] The current from the panels tripped the inverter's hardware protection. Usually a string is bigger than the input is rated for or the input mode is wrong; if the wiring checks out the inverter has an internal fault. Safe steps in the lookup |
Stop and call |
| ID15Sofar ID15 | Grid output overcurrent[1][2] The inverter's output current tripped its hardware protection. The manual treats this as an internal fault: switch off, wait five minutes and restart, and if it comes back the inverter needs an electrician. Safe steps in the lookup |
Stop and call |
| ID17Sofar ID17 | Measuring circuit fault[1] The inverter's circuit that measures grid current, DC injection or grid voltage (ID17, ID18, ID19) is giving bad readings. The manual lists these as internal faults: if a restart does not clear it the inverter needs an electrician. Safe steps in the lookup |
Stop and call |
| ID21Sofar ID21 | Main processor fault[1] The inverter's main control chip has failed its check. If a restart does not clear it the control board has failed and the inverter needs an electrician. Safe steps in the lookup |
Stop and call |
| ID22Sofar ID22 | Internal power supply fault[1] The small power supply that runs the inverter's own electronics is out of range. If a restart does not clear it the inverter needs repair. Safe steps in the lookup |
Stop and call |
| ID25Sofar ID25 | Internal DC bus fault[1] The voltage on the inverter's internal DC bus is too low, too high, unbalanced or not being read (ID23, ID25, ID26, ID27). The manual lists these as internal faults: if a restart does not clear it the inverter needs an electrician. Safe steps in the lookup |
Stop and call |
| ID28Sofar ID28 | DC injection too high[1] The inverter is letting a small amount of DC into its AC output, which the grid rules do not allow. The string manual points first at the input mode setting; if that is right and it keeps coming back the output stage needs testing. DC on the AC side is a protection fault, so we treat it as a call. Safe steps in the lookup |
Stop and call |
| ID29Sofar ID29 | Software overcurrent trip[1] The inverter's software saw an instant of too much current on the grid side (ID29) or the panel side (ID30). A restart may clear a one-off; if it repeats the string size, wiring and inverter need an electrician. Safe steps in the lookup |
Stop and call |
| ID34Sofar ID34 | Backup overload or CT fault[3] On a Sofar HYD hybrid, the appliances on the backup circuit are drawing more than the inverter can supply (ID34), or the CT clamp that measures the house load is loose or fitted backwards (ID35). Reduce the backup load, or have the CT checked. Safe steps in the lookup |
Worth a look |
| ID49Sofar ID49 | Processor readings disagree[1] The inverter's two control processors are reading different values for grid voltage, frequency, DC injection or earth leakage (ID48 to ID52). A one-off after a grid disturbance can be ignored; if it repeats it is an internal fault and the inverter needs an electrician. Safe steps in the lookup |
Stop and call |
| ID53Sofar ID53 | Internal communication fault[1] The processors inside the inverter have stopped talking to each other. If a restart does not clear it the control board needs an electrician. Safe steps in the lookup |
Stop and call |
| ID54Sofar ID54 | Display board communication fault[1] The control board has lost contact with the communication board that runs the display and monitoring. The inverter may keep generating, but if a restart does not clear it the board needs an electrician. Safe steps in the lookup |
Worth a look |
| ID55Sofar ID55 | Output relay fault[1] The relay that connects the inverter to the grid failed its self-test. A restart may clear a one-off; a repeat means the relay or power board has failed, which is a job for an electrician. Safe steps in the lookup |
Stop and call |
| ID65Sofar ID65 | Permanent protection trip[1] The inverter has recorded a fault it treats as unrecoverable: grid overcurrent, bus overvoltage or an unbalance that kept repeating (ID65 to ID70). A restart may clear the screen for a while but it comes back until the inverter is repaired or assessed under warranty. Safe steps in the lookup |
Stop and call |
| ID74Sofar ID74 | Panel overcurrent (locked)[1] The current from the panels tripped the hardware protection so often that the inverter has locked out. It needs an electrician to check the strings and the inverter. Safe steps in the lookup |
Stop and call |
| ID75Sofar ID75 | Memory fault[1] The inverter's settings memory failed a write (ID75) or read (ID76) and it has locked out. If a restart does not clear it the control board needs repair or a firmware reload. Safe steps in the lookup |
Stop and call |
| ID77Sofar ID77 | Output relay failed (locked)[1] The relay that connects the inverter to the grid has failed its self-test so often that the inverter has decided it is faulty. It needs an electrician; this is normally a repair or replacement, not a restart. Safe steps in the lookup |
Stop and call |
| ID95Sofar ID95 | Communication board fault[1] The communication board's memory (ID95) or clock chip (ID96) has failed. The inverter may keep generating, but monitoring and scheduling will be affected; if a restart does not clear it the board needs replacing. Internal and hardware faults need testing with the right instruments, so we treat them as a call. Safe steps in the lookup |
Stop and call |
| ID98Sofar ID98 | SD card fault[1] The memory card that logs the inverter's data is faulty or loose. Generation is not affected; the card needs reseating or replacing. Internal and hardware faults need testing with the right instruments, so we treat them as a call. Safe steps in the lookup |
Stop and call |
| ID57Sofar ID57 | Inverter too hot[1] The inverter's internal, boost-stage or surrounding temperature (ID57, ID58, ID59) went over its limit, so it stopped. Usually it is mounted in direct sun or a hot, closed space; it comes back once it cools, but if it happens on ordinary days the fan or heatsink needs a look. Heat shutdowns point at a failing fan, a blocked vent or a bad installation spot, so we treat them as a call. Safe steps in the lookup |
Stop and call |
The battery, its management system and its state of charge. These only appear on systems with a battery connected. 1 stop and call, 1 worth a look.
| Error code | What it means | What to do |
|---|---|---|
| ID52 BatCommunicationSofar ID52 BatCommunication | Battery communication lost[3] On a Sofar HYD hybrid, the inverter cannot talk to the battery's management system, usually the data cable or the wrong battery type selected. The cable and settings need checking. Safe steps in the lookup |
Worth a look |
| ID85Sofar ID85 | Battery protection event[3] On a Sofar HYD hybrid, the battery has stopped discharging because it reached its set limit or is low (ID85), could not complete a forced charge (ID86), or its own management system tripped on current or temperature (ID100 to ID107). Occasional events clear themselves; frequent ones need the battery settings and installation checked. Heat shutdowns point at a failing fan, a blocked vent or a bad installation spot, so we treat them as a call. Safe steps in the lookup |
Stop and call |
Monitoring, Wi-Fi, meters, communication between parts of the system, settings and firmware. Usually not a hardware fault, but the system may stop reporting. 2 stop and call, 2 worth a look.
| Error code | What it means | What to do |
|---|---|---|
| ID11Sofar ID11 | Panel input setting wrong[1][2] On a Sofar string inverter, the input mode does not match how the strings are wired. On a HYD hybrid the same number is an internal converter overcurrent trip. The installer needs to correct the setting or test the unit. Over-voltage, over-current and short-circuit faults can damage hardware, so we treat them as a call. Safe steps in the lookup |
Stop and call |
| ID71Sofar ID71 | Panel input setting wrong (locked)[1][2] The inverter has locked out because its input mode has been wrong for too long. The installer needs to correct the PV input mode setting to match the string wiring. A protection lockout means the inverter found something it will not run with, so we treat it as a call. Safe steps in the lookup |
Stop and call |
| ID94Sofar ID94 | Firmware mismatch[1] The software on the inverter's control board and communication board do not match, usually after a partial update. Sofar support or a technician needs to update the software. Safe steps in the lookup |
Worth a look |
| ID97Sofar ID97 | Country setting invalid[1] The inverter's grid-standard country setting is missing or invalid, so it will not export. Your installer needs to set the Australian standard. Safe steps in the lookup |
Worth a look |
No Sofar error code matches that. Try the fault code lookup, which also works from a description of what you can see.
Our own licensed electricians cover Greater Adelaide and regional SA, and from North Brisbane up through the Sunshine Coast to Gympie. Check your postcode, then read us the code and tell us the install year. If it needs a visit, the callout is credited against the work.
Try one restart, in this order:
Never open the unit or touch the wiring. Never restart anything that smells hot or shows scorch marks. If the code comes back after one restart, stop and call.
Our electricians test the whole system before they blame the inverter: insulation resistance on every string, earth continuity, the grid relay, DC string voltages and currents, the AC supply and the unit's own fault log. With Sofar that order matters. ID10 and ID11 on a string inverter often come down to the PV input mode setting, and ID56 is usually found on the roof, not inside the box.
Sofar is supported through Australian distributors, so a fault inside the unit is checked for a repair first. Some are repairable and some are not, and a relay that has locked out, ID77, is normally a repair or a replacement rather than a restart. If the inverter cannot be fixed, we quote a straight replacement and a hybrid option side by side, the callout comes off whichever you choose, and the panels usually stay.
We do this work in Adelaide, the Adelaide Hills, Gawler, the Barossa, the Fleurieu, Murray Bridge and Yorke Peninsula in South Australia, or North Brisbane, Caboolture, Bribie Island, the Sunshine Coast, Noosa and Gympie in Queensland only. Outside those areas, everything above still applies: take the code, its meaning and the urgency to a licensed electrician near you.
Every Sofar code on this page was read from the maker's own manual. The numbers match the references in the code table.
Tables last updated
Write down the ID number, then check the label to see whether you have a string inverter or a HYD hybrid. Type the number into the search box above the table, with or without the ID. Where a row says a HYD reads that number differently, go by your model.
ID01 is “grid voltage too high”. The mains voltage at the inverter went above the limit it is allowed to export at, so it disconnected. It reconnects by itself when the grid settles; if it happens most sunny afternoons the cable run or the street voltage needs checking. We rate it wait and watch. See it in the table.
ID12 is “earth leakage fault”. On a Sofar string inverter, the inverter measured current leaking to earth from the solar wiring, usually damaged cable insulation or water in a connector. On a HYD hybrid the same number is a battery overcurrent trip. A one-off in wet weather can clear itself, but a repeat is a safety issue and needs an electrician. We rate it stop and call. See it in the table.
We work in Adelaide, the Adelaide Hills, Gawler, the Barossa, the Fleurieu, Murray Bridge and Yorke Peninsula in South Australia, or North Brisbane, Caboolture, Bribie Island, the Sunshine Coast, Noosa and Gympie in Queensland. Check your postcode to be sure. Outside those areas, this page still tells you what your code means and how urgent it is, and a licensed electrician near you can take it from there.
For homes in our service area, the phone diagnosis is free. If it needs a visit, there is a callout fee, and it is credited against any repair or replacement we do.
Yes, if it is in our service area. Most of our repair work is on systems someone else installed. We test the whole system, not just the unit on the wall.
Sofar’s string inverters and its HYD hybrids use separate fault lists that share numbers. ID12, for example, is an earth leakage fault on a string inverter and a battery overcurrent trip on a HYD. The table gives both where they differ, so check the model on the label before you act on a code.
Sometimes. Sofar is supported through Australian distributors, and many of its codes are the grid, a setting or the string design rather than a broken part. For a fault inside the unit, we will tell you on the phone what is likely and price a replacement beside any repair that is still possible.
From Sofar’s own user manuals for the 3KTLM-G2 to 6KTLM-G2 string inverters and the HYD 3K-ES to 6K-ES hybrids. Every Sofar code on this page comes from those manuals, and each one carries a numbered reference to its document in the source list.
More solar repairs guides from our electricians.
Swipe to see more

All 56 Fox ESS error codes in plain English, across the hybrid inverters, the batteries and the string inverters: what each one means, how urgent it is, how to reset safely, and whether it can still be repaired.
Read more
All 61 Alpha ESS error codes in plain English, from the SMILE inverter and AlphaCloud alarms to the battery’s own error lights: what each one means, how urgent it is, how to reset safely, and whether it can still be repaired.
Read more$0 power bill guarantee
If you are considering solar for a new home, or on behalf of someone else, select "I own my home"
A solar or battery system is a permanent change to the property, so it needs to be arranged by the person who owns the home.
If you tapped that by mistake, head back and we'll pick up where you left off.
Our team can talk you through all options if you're not sure.
You'll get all of these. We'd just like to know what matters most.
The average Adelaide home spends $500 - $1000 per quarter. Not sure of yours? Take your best guess, we'll go through the real numbers at your assessment.
Whatever it is today, our goal is $0. If we don't get you there, we'll pay your bill.
We can work with you on a longer timeline, or get you saving as soon as possible.
We have hundreds of happy customers across South Australia. We need your address to check we service your area and to look at your roof before we visit.
Great news, we service your area!
Every system we design is tailored to the home, so the more info the better! (Optional)
Last step. We'll call to arrange your free on-site assessment at a time that suits you. No pressure and no obligation.
Request sent, we'll be in touch!
Call to speak directly with a solar specialist during business hours, and we can get your free on-site assessment booked in straight away.
📞If you haven't called already, we'll give you a call to say hello.
We'll chat about what you're looking for, how we can help, and book in a time for your on-site assessment that suits you.
We visit your home for 45 to 60 minutes to measure up the roof, check the switchboard and review how you use power.
A tailored proposal with the system design, the savings and the pricing laid out in full.
If you're happy with the proposal, our in-house team installs it and shows you how it all works.